Repairs to the earthen dam at Raymond Park would go to a Garland contractor that promised to finish in 40 days, even though two other firms bid less, under a $287,625 contract on the Town Council's consent agenda Tuesday, Nov. 24.
The dam sits along the park's northeastern edge, about 150 yards west of Coit Road. According to a memo from Parks and Recreation Director David Angeles, the work includes replacing drainage infrastructure, building a concrete junction box, installing a chimney drain, placing and compacting clay fill and lining the slope with rock riprap to protect against erosion.
Price was not the only factor
The town received five proposals by its Oct. 22 deadline. Bernal Commercial Construction of Grand Prairie offered the lowest price, $249,970, but listed 130 days to do the job. Precision Road Services of Southlake came in at $256,480 and 150 days, and Mann Robinson and Sons of Aubrey at $323,729.40 and 120 days. A fifth bid, from Fredericksburg-based Southern Development Corp., was ruled non-responsive.
Garret Shields Infrastructure's proposal of $287,625 carried a 40-day timeline. The town's evaluation matrix weighted cost at 65%, proposed timeline at 25% and qualifications and experience at 10%. Garret Shields scored 9.08 out of 10, ahead of Bernal at 8.00, with its schedule earning full marks in that category.
The memo says the construction price falls within the engineer's estimate but pushes the overall project above its original $350,000 budget. About 78% of the contract is covered by the Raymond Park dam repair account, and the rest would come from savings in the Doe Branch Trails project account.