Back to Texas

Texas Regulators Adopt Batch Zero Plan to Handle Data Center Grid Queue

ERCOT won approval for its new batched-study interconnection process, tackling a 438 GW queue of large-load projects, nearly all from data centers across the state.

Opal Fields

June 30, 20262 min read

Texas power grid transmission lines at sunset over plains — illustration, Jake Team LLC
Texas power grid transmission lines at sunset over plains — illustration, Jake Team LLC

AUSTIN, Texas — The Public Utility Commission of Texas approved ERCOT’s new “Batch Zero” large-load interconnection framework on June 18, 2026, launching the state’s first systematic attempt to manage an unprecedented 438-gigawatt queue of projects seeking to connect to the Texas power grid, nearly 90% of which are data centers.

Prosper, a town of approximately 42,000 in Collin County about 40 miles north of Dallas, is the fastest-growing town in the DFW metroplex with Prosper ISD employing 3,850 people.

The 438 GW tracked by ERCOT represents more than five times the grid’s all-time peak demand of 85,508 megawatts, set in August 2023. ERCOT’s own forecasts had projected peak load reaching 367,790 MW by 2032, driven by more than 250,000 MW of large-load requests.

However, ERCOT officials acknowledged those forecasts are likely inflated, as many projects in the interconnection queue are speculative and may never be built.

Under the new Batch Zero process, ERCOT will study groups of large projects simultaneously rather than evaluating each one individually. Only projects that meet a “maturity criteria”—having secured financing and land—will be eligible for the first batch, with inclusion decisions expected by August 2026.

A final transmission plan for Batch Zero is slated for fall 2027, and a second round of applications will open in summer 2027.

“Texas is experiencing an energy transformation unlike anything we have seen before. This new process represents a fundamental shift in how ERCOT manages the significant growth of large load interconnection, providing a structured, transparent path forward.” — Pablo Vegas, ERCOT President and CEO
“It will be the first step in that solution set actually being defined. We could potentially be solving a national issue on how to do this in a way that can be done reliably, stably, with consideration for the economic growth considerations, with consideration for the cost implications and with consideration for the reliability and stability of the grids that are going to support these assets.” — Pablo Vegas, ERCOT CEO

The reform comes amid growing bipartisan backlash against data center development across Texas. Governor Greg Abbott directed the PUCT and ERCOT in a June 10 letter to shield residential ratepayers from data center infrastructure costs and pledged to pursue legislation in the next session requiring data centers to report their electricity and water usage, use water-efficient technologies, and pay for their own electric infrastructure.

The PUCT and ERCOT were given a July 17 deadline to outline steps taken and identify any statutory limits on their authority.

On the same day the PUCT approved Batch Zero, the Federal Energy Regulatory Commission concluded that most grid operators’ existing rules for large-load interconnections are insufficient, directing them to develop their own frameworks.

Energy analysts have called ERCOT’s approach “the first market design that is ready-to-ship for large loads that actually solves reliability risk, transmission affordability, and siting loads to benefit all ratepayers, simultaneously,” positioning Texas as a potential national model.

Source: https://www.utilitydive.com/news/texas-facing-438-gw-queue-approves-initial-large-load-interconnection-pro/823367/

Share

Opal Fields

Opal Fields covers weather, storms, and seasonal life around Prosper.

Related Stories

Texas

Texas Sets New Record for Total Jobs in June

The Texas Workforce Commission reported that total nonfarm jobs rose to 14,469,600 in June, a gain of 43,400 positions during the month. Over the trailing 12 months, the state added 177,900 jobs and grew faster than the nation as a whole.

Xenia YoderJuly 18, 20261 min read

More in Sport

Sport

Young, Orioles hold off Astros 5-2 in Houston

Baltimore Orioles pitcher Brandon Young delivered a dominant performance, striking out seven batters over seven innings to lead his team to a 5-2 victory over the Houston Astros at Daikin Park.

Quincy NashJuly 20, 20262 min read
Sport

Baldwin, Riley Power Braves Past Rangers 8-5

Austin Riley hit two home runs and Austin Baldwin collected five hits, including two homers, as the Atlanta Braves defeated the Texas Rangers 8-5 at Truist Park on Sunday.

Quincy NashJuly 20, 20262 min read