Manhole sensors would track where extra water gets into the town's sewer lines under a $90,000 study on Tuesday's agenda

The consent item would scan manholes with lidar and log flows for a year to rank problem areas. A separate change order adds $256,520 to First Street work after BNSF required a longer steel casing for a water line.

Gwen Abbott· AI-assisted, edited by Jake Team

October 25, 20262 min read

Prosper civic water study - illustration, Jake Team LLC

Prosper would pay a Utah company $90,000 to put sensors in sewer manholes and measure where unwanted water is getting into the town's wastewater system, under a purchase on the Town Council's consent agenda Tuesday.

The inflow and infiltration study from RH Borden and Company of Lehi, Utah, was requested by the Public Works wastewater division during budget planning and is a budgeted contracted service this fiscal year, according to a staff memo.

Crews would first capture key dimensions of selected manholes with lidar scans. Level sensors would then record how wastewater moves through the pipes to establish what normal flow looks like. When the readings show excess water, the study would estimate how much and compare sensor sites to find the areas with the worst problems.

The vendor's quote also calls for matching water levels against wet-weather records.

Staff would use the results to decide where to look more closely, including where smoke testing could help locate defects, the memo says.

The March 5 quote breaks the cost into $24,000 for a year of flow monitoring at eight basin sites, $54,400 for a targeted assessment that places up to seven level sensors per mile of a chosen basin, $8,400 for crew mobilization and $3,200 to install the sensors. The company's analysis would rank basins and sensor locations by how much excess flow each one adds.

The memo ties the study to the town's Capacity, Management, Operation and Maintenance program under the EPA, which requires Prosper to find and correct weaknesses that could lead to sanitary sewer overflows or unauthorized discharges. Staff wrote that the data should help the town fix problems before they turn into backups or overflows.

First Street change order

The same consent agenda carries a $256,520 change order for First Street between the Dallas North Tollway and Coleman Street, a four-lane divided road with a roundabout at Coleman. Mario Sinacola & Sons Excavating is building it under a contract of about $20.8 million that the council approved Feb. 10.

Most of the added cost, $187,850, pays for 322 more feet of 24-inch steel casing around a water line. BNSF required the casing to run across its entire 300-foot right-of-way rather than only under the existing tracks, the memo says. Another $70,050 covers removal of 2,335 feet of old water line that a quantity error left out of the bid form.

A shorter stretch of line to be abandoned saves $2,030, and one added reducer fitting costs $650.

Staff say the change will be paid from project savings, and the council's capital improvements subcommittee recommended approval.

The council meets at 6:15 p.m. Tuesday at Town Hall, 250 W. First St.

Sources

mccmeetings.blob.core.usgovcloudapi.net

mccmeetings.blob.core.usgovcloudapi.net

Share

Gwen Abbott· AI-assisted, edited by Jake Team

Gwen Abbott covers Prosper city hall, the council, and county government.

Related Stories

More in Texas